Projects
Hôtel Le Saint-Sulpice [SLIDER 01]
Hôtel
Le Saint-Sulpice
Renovating
108
suites on 6 floors
Hôtel Le Saint-Sulpice [SLIDER 02]
Hôtel
Le Saint-Sulpice
A timeline of
14
weeks
Hôtel Le Saint-Sulpice [SLIDER 03]
Hôtel
Le Saint-Sulpice
A timeline of
14
weeks
Hôtel Le Saint-Sulpice [MOBILE 01]
Hôtel
Le Saint-Sulpice
Renovating
108
suites on 6 floors
Hôtel Le Saint-Sulpice [MOBILE 02]
Hôtel
Le Saint-Sulpice
A timeline of
14
weeks
Hôtel Le Saint-Sulpice [MOBILE 03]
Hôtel
Le Saint-Sulpice
A timeline of
14
weeks

Summary

Name: Le Saint-Sulpice Hotel
Location: 414 Saint Sulpice Street, Montreal
Type : Hotel
Mandate : Construction management
Timeline: 2013
Project scope: 108 suites
Client : Le Saint-Sulpice Hotel Owners Association
Architect : MEI Design

Challenges

  • Renovating 108 suites on 6 floors
  • Carrying out the works without interrupting or compromising the hotel’s day-to-day activities
  • Working in Old Montreal, a densely-populated tourist area
Hôtel Le Saint-Sulpice [01]
Hôtel Le Saint-Sulpice [02]
Hôtel Le Saint-Sulpice [03]
Hôtel Le Saint-Sulpice [04]

Le Saint-Sulpice Hotel

In 2012, QMD was selected to renovate all 108 suites in the Saint-Sulpice Hotel in Old Montreal. This mandate involved completely revamping the hotel’s interior decor (wallpaper, paintings, woodwork), upgrading the lighting and replacing furniture (chairs, armchairs, nightstands, lamps, beds and accessories).

The fact that the hotel is located in a densely-populated area made the site access and materials delivery complicated. Furthermore, the works were carried out during a peak season when the Saint-Sulpice Hotel was occupied. Thanks to our experience in hotel renovation projects, we ensured that the works being carried out did not detract from the guest experience. We planned every step and divided up the works into 10 phases in order to limit noise and dust pollution.

We succeeded in delivering the project within the established timeline so our client was very satisfied with the result. The Saint-Sulpice Hotel subsequently contracted QMD to renovate the hotel’s bathrooms and kitchenettes.